top of page

Project Updates & Impacts

Traffic Impacts

​

Traffic Pattern - 900 E / 5600 S Intersection:

​

Traffic on 900 East will shift to the west to allow crews to complete connections between the center lanes and the intersection.

 

One lane of traffic will remain open in each direction on 900 East. During this work, access from 5600 South to 900 East will be closed for approximately 4 weeks* while crews complete these connections.

 

Please plan ahead and use an alternate route when traveling through the area.

​

Business access will be maintained throughout construction.

​

Murray Storm Drain phase 2 detour_v2.png

Ongoing Work

Paving is underway and is anticipated to continue through the rest of the week, weather and conditions permitting.

 

Crews are working toward restoring the road to its normal configuration by next week.

 

In the meantime, drivers should continue to expect temporary lane shifts as crews complete cleanup, minor repairs, and roadway striping throughout the area.

How the Slide Rail System Works

Image (30).jpg
Crews using the slide rail system to install storm drain pipe along Woodoak Lane. 

This project is using a slide rail system to support deep excavation work. The system prevents trench walls and nearby structures from collapsing or caving in by providing stable support.

 

Crews install posts along the trench and excavate in stages, lowering steel panels between the posts using a dig-and-push method. This creates a safe, controlled work zone as the excavation deepens.

 

This approach improves safety and efficiency compared to traditional trenching methods and is especially useful for storm drain installation, where maintaining stable soil conditions is critical.

bottom of page